Colorado has established emissions-reduction and clean-energy requirements. Utilities must plan for future growth while meeting state regulatory requirements related to emissions, renewable energy and resource planning. These requirements influence how generation and infrastructure are developed.
Concern for community is a core cooperative principle.
However, CORE’s authority is limited to providing electric service. Data center developers must satisfy local, state and federal requirements regarding land use, water, environmental considerations and permitting. These requirements are administered by the appropriate governmental agencies and jurisdictions.
No.
CORE’s current transmission and infrastructure projects are designed to maintain reliability, improve resiliency, support generation and storage resources, and accommodate expected system growth. Planned projects were not developed specifically for data center loads.
Typically, no.
Large-load projects require extensive engineering reviews and feasibility studies. Utilities must ensure that sufficient transmission, substation and power supply resources exist before service can be provided. Depending on a project’s complexity, due diligence and planning can take many months.
CORE rates generally include three components:
- Service charge
- Energy charge
- Demand charge
These components are designed to reflect the cost of providing electric service and help ensure members pay based on their actual use and impact on the system.
No.
CORE carefully evaluates all large-load requests to ensure reliability remains the top priority. Service is only provided if sufficient transmission, generation and distribution resources are available to maintain reliable service for all members.
CORE incorporates multiple safeguards into agreements with large-load customers. These may include:
- Financial security
- Long-term service commitments
- Minimum load requirements
- Phased growth schedules
- Other financial security measures
These protections help ensure project costs are recovered and reduce risk to the cooperative and its members.
The data center developer pays for infrastructure required to serve its project.
This may include substations, interconnection facilities, transmission upgrades and other dedicated equipment. These costs are assigned to the project and are not added to CORE’s general system costs for other members.
No. Data centers do not automatically increase electric rates.
CORE uses cost-based rates, meaning each member class pays their fair share based on the cost to serve them. Large-load customers, including data centers, are responsible for the costs associated with serving their facilities.
CORE evaluates every opportunity using the same principles:
- Maintain reliability for existing members
- Ensure members do not subsidize project costs
- Require developers to fund project-specific infrastructure
- Mitigate financial risk
- Meet regulatory and policy requirements
- Support responsible, sustainable growth
As a member-owned cooperative, CORE’s priority is to protect members while planning for the future energy needs of the communities we serve.