CORE Electric Cooperative has sought the approval of Douglas County to build, operate and maintain a new substation and linked battery energy storage system (BESS) near the intersection of North Ridge Road and East Plum Creek Parkway in Castle Rock.
The proposed Eastern Plains Reliability Upgrade (EPRU) will replace the existing Strasburg Transmission to Deer Trail 44-kilovolt transmission line with the Wolf Creek to Rattlesnake Creek 115kV transmission line. EPRU will also replace the existing Strasburg Transmission Substation with the new Wolf Creek Substation, and the Deer Trail Substation with the new Rattlesnake Creek Substation. Four routing options will be analyzed for the new 115kV transmission line between the proposed Wolf Creek and Rattlesnake Creek substations. Visit the Eastern Plains Reliability Upgrade website for additional information.
The new Spring Valley Substation and 115-kilovolt double circuit transmission line will improve and provide reliable electricity to members in and around northwest Elbert County. The project construction is complete and was energized in February 2026.
CORE will rebuild 9 miles of existing 44-kilovolt transmission line to 115 kilovolts to improve reliability and capacity. Permitting and land rights activities are under way. The project is delayed until the U.S. Forest Service (USFS) determines a solution to resolve nationwide staffing shortages. A second open house meeting will be scheduled once new route options are proposed and discussed with the USFS.
This 11-mile rebuild project started construction in September 2026 and should be completed by April 2027. The existing line will be rebuilt to improve capacity and reliability for the Douglas County area.
CORE will rebuild the existing Shawnee Substation from 44 kilovolts to 115 kilovolts to improve capacity and reliability. The state land board lease agreement is finalized, and payments began in 2025 for new substation limits. County permitting and the substation design are delayed until the U.S. Forest Service determines a solution to resolve nationwide staffing shortages that also impact the Roberts Tunnel – Shawnee 115kV transmission line.
CORE Electric Cooperative has sought the approval of Douglas County to build, operate and maintain a new substation and linked battery energy storage system (BESS) near the western end of Timber Mill Parkway in Castle Rock.
The redesign and rebuild of the 115-kilovolt transmission line between our Waterton and Roxborough substations was completed and energized in early 2026.
A new 115kV double circuit transmission line will connect CORE’s existing Citadel Substation and a new substation located within the Dawson Trails development. Construction is expected to start in late 2027, and the line energized in Summer 2028.