Does Colorado have enough electric capacity to support unlimited growth?

Typically, no. 

Large-load projects require extensive engineering reviews and feasibility studies. Utilities must ensure that sufficient transmission, substation and power supply resources exist before service can be provided. Depending on a project’s complexity, due diligence and planning can take many months.

How are electric rates structured?

CORE rates generally include three components: 

  • Service charge 
  • Energy charge 
  • Demand charge 

These components are designed to reflect the cost of providing electric service and help ensure members pay based on their actual use and impact on the system.

Will a data center affect reliability or increase outages?

No. 

CORE carefully evaluates all large-load requests to ensure reliability remains the top priority. Service is only provided if sufficient transmission, generation and distribution resources are available to maintain reliable service for all members.  

How does CORE protect members from financial risk?

CORE incorporates multiple safeguards into agreements with large-load customers. These may include: 

  • Financial security
  • Long-term service commitments
  • Minimum load requirements
  • Phased growth schedules
  • Other financial security measures

These protections help ensure project costs are recovered and reduce risk to the cooperative and its members.

Who pays for infrastructure upgrades needed to serve a data center?

The data center developer pays for infrastructure required to serve its project.

This may include substations, interconnection facilities, transmission upgrades and other dedicated equipment. These costs are assigned to the project and are not added to CORE’s general system costs for other members.

Do data centers increase electric rates?

No. Data centers do not automatically increase electric rates. 

CORE uses cost-based rates, meaning each member class pays their fair share based on the cost to serve them. Large-load customers, including data centers, are responsible for the costs associated with serving their facilities.